#### Scheduling Algorithms
|
||||||
|
- A schedule is feasible if all the tasks start after their release time and complete before their deadlines
|
||||||
|
- Rate-Monotonic Scheduling (RM)
|
||||||
|
- A model for optimal static priority scheduling algorithm
|
||||||
|
- Not straight-forward when it comes to guarantee the feasibility of a task schedule
|
||||||
|
- Use this algorithm if task priorities **do not** change
|
||||||
|
- The scheduling decision is made when the current task execution is complete and a new task is released
|
||||||
|
- The task utilisation is execution time divided by period
|
||||||
|
- The CPU utilisation for the schedule is just the sum of all of these
|
||||||
|
- The smallest period is the highest priority for all released tasks
|
||||||
|
- Tasks are pre-empted if a higher-priority task is released
|
||||||
|
- A general schedulability test for RM is $$
|
||||||
|
U \leq n \left( 2^{\frac{1}{n}} - 1 \right)
|
||||||
|
$$
|
||||||
|
where $n$ is the number of tasks
|
||||||
|
- If this is true, a feasible schedule is guaranteed, no need for further analysis
|
||||||
|
- Otherwise, you need to actually check feasibility
|
||||||
|
- This can be done by checking $$
|
||||||
|
W_{i}(t) = \sum_{j = 1}^{i} e_{j} \left( \frac{t}{p_{j}} \right) \leq t
|
||||||
|
$$
|
||||||
|
for task interval $t$ and number of tasks $i$
|
||||||
|
- $\frac{t}{p_{j}}$ is always **rounded up**
|
||||||
|
- Check each of the points to see which tasks cause infeasibility which may include repeats of periods
|
||||||
|
- In other words, you can check whether 2 tasks will work in the period for
|
||||||
|
- The schedule is feasible if this is true
|
||||||
|
- Earliest Deadline First (EDF)
|
||||||
|
- Use this algorithm if task priorities **do** change over time
|
||||||
|
- Also preemptable
|
||||||
|
- The tasks with the earliest absolute deadline are given highest priority
|
||||||
|
- Priorities are re-evaluated when tasks are released or completed
|
||||||
|
- This is an optimal single-processor scheduling algorithm
|
||||||
|
- If $U \leq 1$ then the task set is schedulable
|
||||||
|
|
||||||
|
|
||||||
|
|
||||||
|
#### Scheduling Example from Paper
|
||||||
|
| t | e | p |
|
||||||
|
| --- | --- | --- |
|
||||||
|
| 1 | 10 | 50 |
|
||||||
|
| 2 | 20 | 100 |
|
||||||
|
| 3 | 30 | 150 |
|
||||||
|
| 4 | 40 | 200 |
|
||||||
|
**CE**
|
||||||
|
Must execute tasks every 50 ms
|
||||||
|
|
||||||
|
1 + 4 = 50 so we need these to be on their own every time
|
||||||
|
|
||||||
|
2 + 3 = 50 so these also need to be on their own
|
||||||
|
|
||||||
|
is this even possible?
|
||||||
|
|
||||||
|
it will have overruns - 4 has to be split into 2 subtasks
|
||||||
|
|
||||||
|
| t | e | p |
|
||||||
|
| --- | --- | --- |
|
||||||
|
| 1 | 10 | 50 |
|
||||||
|
| 2 | 20 | 100 |
|
||||||
|
| 3 | 30 | 150 |
|
||||||
|
| 4a | 20 | 200 |
|
||||||
|
| 4b | 20 | 200 |
|
||||||
|
|
||||||
|
|
||||||
|
1 has to be called every time since the period is 50
|
||||||
|
|
||||||
|
|
||||||
|
| time | tasks | |
|
||||||
|
| ---- | -------- | --- |
|
||||||
|
| 0 | 1, 2, 4a | |
|
||||||
|
| 50 | 1, 4b | |
|
||||||
|
| 100 | 1, 2 | |
|
||||||
|
| 150 | 1, 3 | |
|
||||||
|
| 200 | 1, 2, 4a | |
|
||||||
|
| 250 | 1, 4b | |
|
||||||
|
| 300 | 1, 2 | |
|
||||||
|
| 350 | 1, 3 | |
|
||||||
|
|
||||||
|
|
||||||
|
|
||||||
|
**RM**
|
||||||
|
Total Utilisation: $$
|
||||||
|
\sum_{i = 1}^{n} u_{i}:u_{i} = \frac{e_{i}}{p_{i}}
|
||||||
|
$$
|
||||||
|
$$
|
||||||
|
0.2 + 0.2 + 0.2 + 0.2 = 0.8
|
||||||
|
$$
|
||||||
|
$$
|
||||||
|
0.8 \leq n(2^{1/n} - 1)
|
||||||
|
$$
|
||||||
|
$$
|
||||||
|
0.8 > 0.76
|
||||||
|
$$
|
||||||
|
$$
|
||||||
|
W_{4} = \{50, 100, 150, 200\}
|
||||||
|
$$
|
||||||
|
$$
|
||||||
|
W_{4}(t) = \sum_{j = 1}^{4} e_{j} \left( \frac{t}{p_{j}} \right)
|
||||||
|
$$
|
||||||
|
$$
|
||||||
|
= 10(4) + 20(2) + 30(2) + 40(1)
|
||||||
|
$$
|
||||||
|
$$
|
||||||
|
= 180 < 200
|
||||||
|
$$
|
||||||
|
this is feasible
|
||||||
|
|
||||||
|
| time | task running | tasks available | |
|
||||||
|
| ---- | ------------ | --------------- | --- |
|
||||||
|
| 0 | 1 | 1, 2, 3, 4 | |
|
||||||
|
| 10 | 2 | 2, 3, 4 | |
|
||||||
|
| 20 | 2 | 2, 3, 4 | |
|
||||||
|
| 30 | 3 | 3, 4 | |
|
||||||
|
| 40 | 3 | 3, 4 | |
|
||||||
|
| 50 | 1 | 1, 3, 4 | |
|
||||||
|
| 60 | 3 | 3, 4 | |
|
||||||
|
| 70 | 4 | 4 | |
|
||||||
|
| 80 | 4 | 4 | |
|
||||||
|
| 90 | 4 | 4 | |
|
||||||
|
| 100 | 1 | 1, 2, 4 | |
|
||||||
|
| 110 | 2 | 2, 4 | |
|
||||||
|
| 120 | 2 | 2, 4 | |
|
||||||
|
| 130 | 4 | 4 | |
|
||||||
|
| 140 | | | |
|
||||||
|
| 150 | 1 | 1, 3 | |
|
||||||
|
| 160 | 3 | 3 | |
|
||||||
|
| 170 | 3 | 3 | |
|
||||||
|
| 180 | 3 | 3 | |
|
||||||
|
| 190 | | | |
|
||||||
|
| 200 | 1 | 1, 2, 4 | |
|
||||||
|
| 210 | 2 | 2, 4 | |
|
||||||
|
| 220 | 2 | 2, 4 | |
|
||||||
|
| 230 | 4 | 4 | |
|
||||||
|
| 240 | 4 | 4 | |
|
||||||
|
| 250 | 1 | 1, 4 | |
|
||||||
|
| 260 | 4 | 4 | |
|
||||||
|
| 270 | 4 | 4 | |
|
||||||
|
| 280 | | | |
|
||||||
|
| 290 | | | |
|
||||||
|
| 300 | 1 | 1, 3 | |
|
||||||
|
|
||||||
|
|
||||||
|
**EDF**
|
||||||
|
$$
|
||||||
|
0.8 < 1
|
||||||
|
$$
|
||||||
|
this is feasible
|
||||||
|
|
||||||
|
| time | task running | tasks available | |
|
||||||
|
| ---- | ------------ | --------------- | --- |
|
||||||
|
| 0 | 1 | 1, 2, 3, 4 | |
|
||||||
|
| 10 | 2 | 2, 3, 4 | |
|
||||||
|
| 20 | 2 | 2, 3, 4 | |
|
||||||
|
| 30 | 3 | 3, 4 | |
|
||||||
|
| 40 | 3 | 3, 4 | |
|
||||||
|
| 50 | 1 | 1, 3, 4 | |
|
||||||
|
| 60 | 3 | 3, 4 | |
|
||||||
|
| 70 | 4 | 4 | |
|
||||||
|
| 80 | 4 | 4 | |
|
||||||
|
| 90 | 4 | 4 | |
|
||||||
|
| 100 | 1 | 1, 2, 4 | |
|
||||||
|
| 110 | 2 | 2, 4 | |
|
||||||
|
| 120 | 2 | 2, 4 | |
|
||||||
|
| 130 | 4 | 4 | |
|
||||||
|
| 140 | | | |
|
||||||
|
| 150 | 1 | 1, 3 | |
|
||||||
|
| 160 | 3 | 3 | |
|
||||||
|
| 170 | 3 | 3 | |
|
||||||
|
| 180 | 3 | 3 | |
|
||||||
|
| 190 | | | |
|
||||||
|
| 200 | 1 | 1, 2, 4 | |
|
||||||
|
| 210 | 2 | 2, 4 | |
|
||||||
|
| 220 | 2 | 2, 4 | |
|
||||||
|
| 230 | 4 | 4 | |
|
||||||
|
| 240 | 4 | 4 | |
|
||||||
|
| 250 | 1 | 1, 4 | |
|
||||||
|
| 260 | 4 | 4 | |
|
||||||
|
| 270 | 4 | 4 | |
|
||||||
|
| 280 | | | |
|
||||||
|
| 290 | | | |
|
||||||
|
| 300 | 1 | 1, 3 | |
|